Despite some reports of increasing enquiries and workload, lead times have held steady for the most part as suppliers try to stay competitive. Brian Moone of Mace reports
01 / GOING UP
- Specialist bespoke joinery
02 / STAYING LEVEL
- Piling (rotary)
- Piling (pre-cast)
- Concrete works
- Structural steel frames
- Cladding - natural materials
- Cladding - metal panellised
- Cladding - curtain walling systems
- Atrium roofs
- Roof finishes - asphalt/membrane
- Roof finishes - profiled metal
- Brickwork
- Blockwork
- Metal doors
- Dry lining
- Demountable partitions
- General joinery
- Raised floors
- Suspended ceilings
- Architectural metalwork
- Decorative wall coverings
- Internal stone flo