Client: The Terrace Hill Group
Architect: Waring & Netts
Main contractor: Shepherd Construction
Project: A new campus for Stockton Riverside College
Budget: £16.5³¾
Time: 72 weeks
Handover: 18 November
Contract type: JCT with design ad ons
Weight of steel trees: 6.5 tonnes
Length of roof: 78m down the north block, 56m down the south block
Cost of the roof: £680,000
Length of fabrication: 4 weeks
Length of installation:4 weeks
Steelwork design: EMP
Roof fabricator and installer: Monkbridge Construction
Structural engineer: Ove Arup