Grenfell architect ‘not asked about high-rise resi cladding experience’ before appointment
Inquiry barrister tells TMO director it was the ‘obvious question’
-
News
Change now if you want to survive the new building safety regulator, Hackitt tells firms
Legislation due before parliament later this autumn
-
News
Consultant warned Grenfell client project would fail without fundamental reappraisal
Artelia initially said re-tendering job to overcome £2m budget deficit was not the solution – before performing a ‘volte-face’
-
News
Grenfell Inquiry: What we learned this week
Witnesses included consultants from QS Artelia and RBKC’s building control manager
-
News
Grenfell client chose not to hire design adviser which would have cost £30,000
TMO ‘struggled with design issues’ after rejecting outside help, inquiry heard
-
News
Ðǿմ«Ã½ safety minister slams ‘despicable practices’ exposed by Grenfell
Stephen Greenhalgh tells construction industry to ‘raise its game’ and pioneer offsite methods
-
News
Grenfell consultant had ‘never worked with such a nonchalant contractor’
QS complained final stage of Rydon’s refurb was ‘becoming a farce’
-
News
Contact between client and Rydon was ‘irregular and improper,’ cost consultant tells Grenfell Inquiry
Advisor ‘shocked’ to learn of £800k value engineering talks with future main contractor while OJEU process was still live
-
News
Inquiry hears boss had ‘every confidence’ in Grenfell building control officer
Council manager says surveyor only had 30 live projects and rejects allegations of ‘culture of bullying’
-
News
Trade bodies threaten to boot members out if they can’t prove competence
Focus on firms' abilities follow series of recommendations made following 2017 Grenfell fire
-
News
Grenfell Inquiry: What JRP, Osborne Berry and building control told us this week
Cladding fitters unable to explain ‘unacceptable’ errors while austerity staffing cuts hampered building control inspections
-
News
Ðǿմ«Ã½ control officer ‘needed more time’ to focus on Grenfell refurb
‘Heartbroken’ council surveyor blasts staffing cuts and ‘confusing’ regulations but accepts his checks fell short
-
News
Grenfell inquiry: What we learnt from September’s evidence
Focus was on Harley Facade’s lack of technical expertise, while Max Fordham, Osborne Berry and CEP Architectural Facades also had questions to answer
-
News
Council austerity measures meant inspection corners were cut, Grenfell Inquiry told
Ðǿմ«Ã½ control officer had 130 projects to keep track of and felt forced to make ‘judgments’ about whose work needed most focus
-
News
Grenfell building control officer ‘quit because of work pressures’
Council surveyor tasked with inspecting work tells inquiry he resigned weeks before 2017 disaster
-
News
Grenfell subcontractor ‘can’t see how’ cavity barriers were fitted wrongly
Inquiry hears firm sent in invoice for eight men pretending to work during one day
-
News
Grenfell Inquiry: Window reveal contractor ‘assumed materials were fine’
Former Rydon project manager oversaw gaps being packed with combustible insulation then topped with uPVC surrounds
-
News
Consultant tells Grenfell Inquiry it was ‘crystal clear’ firm was not providing full clerk of works role
John Rowan Partners boss says ‘too many experts’ would have been required to check compliance with all Ðǿմ«Ã½ Regulations
-
News
September week three: What Harley, CEP and Max Fordham told the Grenfell Inquiry
Facades specialist questioned on project management failings and reliance on advice from suppliersÂ
-
News
M&E consultant suggested combustible insulation for Grenfell Tower refurb
Safe mineral wool product ruled out because ‘aspirational’ efficiency target would not have been hit, inquiry hears