Construction and PM group to target rail market while T&T lines up further aviation work
Mace has developed a post-T5 strategy to employ the 200 workers it has assigned to the project once the job starts wrapping up in 2008. The firm will expand its rail operation, Mace Rail, which it believes will be able to use the skills of its army of Heathrow Terminal 5 project managers.
Mace Rail is currently about 40-strong and sits in the firm鈥檚 infrastructure division.
Mace said its rail business was already starting to pick up. It has just won a deal to project manage two depots in Kent with a combined value of 拢90m. The depots at Ashford and Ramsgate are for client HSBC Rail, which has a 30-year lease arrangement.
The firm is also anticipating a rail boom in Russia and Eastern Europe, where it hopes to pick up swathes of business in the coming years.
As a key plank in the post-T5 strategy, Mace hired Dean Benson as operations director, infrastructure, in July from Turner & Townsend, where he led the rail business.
Benson said that of roughly 200 Mace staff working at Heathrow, 50 had direct experience of the rail sector, having worked with clients such as London Underground and Network Rail. 鈥淭he others are transferable. It gives Mace a solid base in the regulated transport sector.鈥
It is not certain that all 200 T5 staff will transfer to Mace Rail, however, as the strategy depends on how much rail business Mace wins and some may be needed for further work for the British Airports Authority (BAA).
Other UK rail PM contracts under Mace鈥檚 belt include the construction of a new station at Deptford, currently underway for Network Rail and a framework deal won from Transport for London, likely to see the firm work on the tube, buses, trams and roads.
We have been working with BAA on a managed ramp down to bring staff off gradually
Bruce McAra, Director of cost management, Turner & Townsend
Turner & Townsend has between 70 and 80 staff assigned to T5, ranging from director to graduate level and comprising cost and project managers and experts in project controls and planning. They will be gradually transferred to the firm鈥檚 other aviation jobs, such as terminals one and three at Gatwick and the redevelopment of Stansted, on which T&T is the cost manager. They may also work on Thames Gateway schemes.
Bruce McAra, the firm鈥檚 director of cost management, said: 鈥淲e have been working with BAA on a managed ramp down to bring staff off gradually. We don鈥檛 want to lose the knowledge they have gained of the sector, methods of working and partnering ethos.鈥
EC Harris, which is also working on the Heathrow project, confirmed it did have a post-T5 strategy in place, but would not reveal it before talking to the staff concerned.
At Mace, Rob Ewen, director of infrastructure sector and the Midlands said his firm first got into the rail business over four years ago, but now the plan was to 鈥渞ebuild our position in the rail sector鈥.
He said Mace had an edge because its project managers tended to have backgrounds in construction rather than QSing or engineering. He added that rail work was becoming higher profile: 鈥淧eople used to see it as mundane, but it鈥檚 the key to most regeneration schemes.鈥
Mace is expecting some of its T5 staff to come off the project from Christmas 2005. T5 is being constructed in two phases: Phase one will open in 2008 with the completion of the main terminal (T5A) and first satellite building (T5B), phase two will open in 2011 with the construction of the second satellite building (T5C).
Source
QS News