All crossrail articles – Page 2
-
News
Crossrail renews construction push following trial running delay
Testing of trains along the route started last week, six weeks after originally scheduled
-
News
Vinci blames revenue drop on pandemic and delays to HS2 and Crossrail work
But profit at civils business jumps as firm eyes growing workload
-
News
Problems at Bond Street putting Crossrail opening at risk, Jacobs warns
Paddington contractor Costain Skanska also meeting railway bosses three times a week over productivity concerns
-
News
Light at the end of the tunnel as Crossrail finally enters key testing phase
Delayed railway due to open in first half of next year
-
News
Former Crossrail chief who came under fire for late-running scheme joins Laing O’Rourke
Andrew Wolstenholme was criticised by politicians after it emerged scheme would miss opening deadline and be billions over budget
-
News
BBA appoints former Crossrail manager under planned rejig
Certifier hires new operations director as part of promised overhaul
-
News
Crossrail risk management still a concern, London Assembly warns
Transport committee publishes report into £18.6bn project’s progress
-
News
MPs doubt industry's ability to build £600bn infrastructure pipeline
Report highlights risk that tax payers will not get value for money from major projects
-
News
Crossrail brings in Bechtel veterans to help get delayed job finished
Railway turns to US engineer to fill key roles on project
-
News
Probe into costs of major transport jobs launched by MPs
Written evidence due back by 15 January
-
News
Critical Crossrail staff kept apart to ensure late-running job not hit with covid delays
Measures put in place to make sure entire teams are not struck down at once with virus
-
News
Government’s chief construction advisor blames dithering ministers for mega-project delays
Comments come as IPA boss said he told Highways England to rethink timetable for £8bn Lower Thames Crossing
-
News
Crossrail 2 staff redeployed as TfL winds up consultancy work on project
Move made as part of recent funding agreement between TfL and government
-
News
Pictures reveal Crossrail progress during construction blockade
Project leadership put initiative in place to claw back time lost to covid-19
-
News
Former Crossrail commercial director handed £77,000 compensation package
Paul Grammer left railway last April to set up own QS business
-
News
Crossrail chairman calls for rethink over how mega-projects are scheduled
Tony Meggs adds original December 2018 deadline caused ‘mayhem’ on railway
-
News
Crossrail chair says Costain and Skanska have helped cause Bond Street delay
Railway bosses confirm station will only be ready some time after rest on central section of line
-
News
New Crossrail opening date and price tag to be firmed up next month
Job has already missed three openings while cost looks set to top £19bn
-
-
News
Crossrail criticised for ‘lack of urgency’ in covid-19 recovery planning
Jacobs also raises concerns about cost and programme management