Recreation building - Gross internal floor area 2100 m2 - 1970s design |
Location | Item | Quantity | Rate | Total £ | Priority £ - High | Priority £ - Medium |
Entrance lobby | Disabled parking bays with dropped kerb: | Ìý | Ìý | Ìý | Ìý | Ìý |
| Disabled parking bay | 2 | 750 | 1,500 | 1,500 | – |
| Dropped kerb | 2 | 200 | 400 | 400 | – |
| Sign on pole | 2 | 120 | 240 | 240 | – |
| Provide handrails and balustrade to side of ramp | 3 m | 200 | 600 | 600 | – |
| Provide kerb to side of ramp | 3 m | 50 | 150 | 150 | – |
| Paint bollards to improve contrast | 5 | 30 | 150 | 150 | – |
| Take up and relay broken paving | 100 m2 | 30 | 3,000 | 3,000 | – |
| Lay new footpath | 30 m2 | 50 | 1,500 | 1,500 | – |
| Paint high contrast bands around columns | 57 m | 10 | 570 | 570 | – |
| Provide new automatic doors | 4 | 8,000 | 32,000 | 32,000 | – |
| Provide paved access to sports grounds | 200 m2 | 30 | 6,000 | 6,000 | – |
| Paint ramp to indicate landing | 5 m | 10 | 50 | – | 50 |
Reception | Lower section of reception desk | 1 | 1,500 | 1,500 | 1,500 | – |
| Provide locational signage | 10 | 15 | 150 | 150 | – |
| Provide tactile signage generally | 6 | 50 | 300 | 300 | – |
| Remove existing portable noticeboard | 2 | 50 | 100 | 100 | – |
| Provide new permanently fixed noticeboard | 2 | 200 | 400 | 400 | – |
Fitness room | Move equipment to ensure circulation space | 1 | 100 | 100 | 100 | – |
Swimming pool | Line marking to edge of pool | 200 m | 10 | 2,000 | 2,000 | – |
Catering | Lower kitchen base unit | 1 | 500 | 500 | 500 | – |
| Replace carpet to improve contrast | 45 m2 | 25 | 1,130 | 1,130 | – |
| Replace cupboard doors with sliding doors | 1 | 100 | 100 | 100 | – |
| Provide armless chairs to viewing area | 4 | 200 | 800 | 800 | – |
| Provide lower kitchen unit for microwave | 2 | 500 | 1,000 | 1,000 | – |
Changing area | Provide accessible facilities to public and staff | Ìý | Ìý | Ìý | Ìý | Ìý |
| male and female changing rooms: | Ìý | Ìý | Ìý | Ìý | Ìý |
| Convert toilet for disabled | 4 | 2,500 | 10,000 | 10,000 | – |
| Shower cubicle with floor drainage and pull–down seat | 4 | 4,000 | 16,000 | 16,000 | – |
| Changing cubicle | 4 | 1,000 | 4,000 | 4,000 | – |
Signage | Improve signage throughout whole building | 50 | 15 | 750 | 750 | – |
Internal doors | Provide new single doorsets including enlarge | Ìý | Ìý | Ìý | Ìý | Ìý |
| existing structural opening | 6 | 1,350 | 8,100 | 8,100 | – |
| Replace existing pairs of double doorsets with | Ìý | Ìý | Ìý | Ìý | Ìý |
| new 1.5 doorsets | 8 | 600 | 4,800 | – | 4,800 |
| Enlarge existing single door opening and | Ìý | Ìý | Ìý | Ìý | Ìý |
| provide new door | 1 | 1,100 | 1,100 | 1,100 | – |
Staircases | Provide new internal stairs | 1 | 22,500 | 22,500 | – | 22,500 |
Fire exits | Provide new ramps to fire exits | 6 | 500 | 3,000 | – | 3,000 |
Lift | Provide new two-storey lift | 1 | 70,000 | 70,000 | – | 70,000 |
| Subtotal for recommendations in access report | Ìý | Ìý | Ìý | 94,140 | 100,350 |
| Add preliminaries @ 20% | Ìý | Ìý | Ìý | 18,830 | 20,070 |
| Subtotal | Ìý | Ìý | Ìý | 112,970 | 120,420 |
| Add contingencies @ 15% | Ìý | Ìý | Ìý | 16,950 | 18,060 |
| Subtotal | Ìý | Ìý | Ìý | 129,920 | 138,480 |
| Above excludes professional fees and VAT | Ìý | Ìý | Ìý | Ìý | Ìý |